Ayos – Kobdombo and Carrefour Ngalla – Ebolboum – Ngoulkeka electrification
Rehabilitation and extension of the Ayos – Kobdombo power network, officially commissioned in December 2021.
Provisional acceptance · 29 July 2021
Works
Rehabilitation of the Ayos – Kobdombo power network and electrification of the Carrefour Ngalla – Ebolboum – Ngoulkeka axis.
Accepted scope
On the first section, 240 poles of 11 m, rigid insulators, almelec conductor and household connections; on the second, a medium-voltage line and five single-phase transformers.
Milestones
- Provisional acceptance — 29 July 2021
- Official commissioning — 21 December 2021, with the network operator and the Ministry of Water and Energy
Project narrative
In spring 2021, the Ayos – Kobdombo network was in poor condition: broken or burnt wooden supports along the axis. The contract combined two jobs: rehabilitating this network and electrifying a new axis, from Carrefour Ngalla to Ngoulkeka. On 29 July 2021, the acceptance committee recorded 240 poles of 11 m in place, the insulators, the almelec conductor and household connections, as well as the medium-voltage line and five transformers on the second section. On 21 December 2021, official commissioning was recorded in the presence of the network operator and the Ministry of Water and Energy.

Other projects
Akonolinga – Minlo electrification, phase I
Three-phase medium-voltage network, six H61 substations and low-voltage networks on the Akonolinga – Minlo axis (Nyong-et-Mfoumou).
Location
Nyong-et-Mfoumou · Centre
Soa – Essé MV/LV network extension
Extension of a three-phase overhead medium- and low-voltage network between Soa and Essé (Méfou-et-Afamba).
Location
Méfou-et-Afamba · Centre
Minlop – Endom electrification, phase II
Three-phase electrification on concrete poles along the Minlop – Endom axis (Nyong-et-Mfoumou), phase II.
Location
Nyong-et-Mfoumou · Centre